Concor has successfully completed South Africa’s second Radisson RED hotel – this one is situated in the vibrant Oxford Parks mixed-use precinct in Rosebank, Johannesburg.
The upmarket 222 room hotel has been designed – like all Oxford Parks Precinct buildings – to meet a minimum five-star Green Star rating. It will open its doors to guests in June, two months after Concor handed over the building in April 2020. This follows the success of the country’s first Radisson RED hotel – located at the Cape Town Waterfront – which opened in 2017.
Concor took the project through to furniture, fitting and equipment (FF&E) stage, including beds, chairs, television sets and the physical backbone for WiFi connectivity, according to Martin Muller, contract manager at Concor.
“The basements for the building were completed as part of the first two phases of the Oxford Parks Precinct, and construction began in October 2019 with the superstructure, from ground floor up,” says Muller. Although the Covid-19 lockdown delayed the project somewhat, construction progressed well on this fast track project. A combination of good planning and full resourcing made this possible, he says, with about 500 people on site at peak including contractors.
Comprising seven levels on top of a ground floor, as well as a roof level for plant and services, the building is a concrete structure based on post-tensioned slabs with grids to suit the room sizes. At the core of the building are four lifts: a goods lift, a fireman’s lift and two lifts for guests.
The ground floor includes the reception, restaurant, kitchens, back-of-house facilities and conference rooms, with the first level housing the management offices, staff facilities and more conference space. Floors two to six each comprise 40 rooms, while on the seventh floor there are just 22 rooms sharing the level with a pool, terrace bar and gym.
“The compact design means that the majority of plant is located on the roof – the eighth level – including water tanks and all the heating, ventilation and cooling (HVAC) systems,” he says.
A curtain-wall system of aluminium frames and double glazed windows characterises the east and west sides of the hotel. On the north- and south-facing sides is a facebrick patterned façade with punch-out square windows.
“Most of the internal partitions are constructed with dry-walling materials of high acoustic and fire-rated properties,” he says. “The specifications for these are highly technical, to avoid any noise transfer from room to room despite the compact design.”
Concor’s work was guided by two sets of specifications, one for back-of-house and another for front-of-house, he notes. The base build spec was provided by dhk Architects, while the interior design spec for the rooms was by Source IBA.
“Keeping a quality building process on track demands a constant focus on information sharing with consultants and subcontractors alike,” says Muller. “This meant weekly meetings to align our building plans with any design adjustments, so we could avoid rework that could have slowed the pace and added to the cost.”
The speed of the project was enhanced by having one tower crane on site, facilitating the work of all trades through the quick delivery of concrete and other materials to the various levels. He highlights the importance of the quality assurance and quality control (QA/QC) teams that followed production and streamlined the snagging process, so that the fit-out specialists could move in to progress the rooms.
“This allowed the production workers to fully complete their tasks before the entry of plumbers, tilers, painters, joiners, electricians and other finishing trades,” he says. Sequencing was conducted in an east-to-west direction, and these teams completed eight rooms at a time.
The Radisson RED project also provided an opportunity for Concor to conduct enterprise development among selected subcontractors. Working with three local small businesses, Concor was able to transfer skills in 18 of the required trades, including brickwork, painting and final handover preparation.
More news
- PART 2: DESIGN AND CONSTRUCTION OF SLAB-ON-GROUND: APPLYING ACI 318
- DESIGN AND CONSTRUCTION OF SLAB-ON-GROUND: APPLYING ACI 318
- DOK-ING’s innovative electric mining equipment unveiled at ElectraMining
- CONCOR’S MASTERY IN FAST TRACK PROJECT IMPLEMENTATION UNDERSCORED BY SAFETY AWARD
- PROMINENT SEA POINT HOTEL REFURBS WITH REHAU